Feature/bug: Building scheduler can double book resources on blocked reservation

Discussions about the Calendar Tool at lds.org. Questions about the calendar on the classic site should be posted in the LUWS forum.
Post Reply
dshep2020
Member
Posts: 293
Joined: Mon Jan 22, 2007 11:43 pm

Feature/bug: Building scheduler can double book resources on blocked reservation

#1

Post by dshep2020 »

After the recent update, Calendar 2.0.1 Release (Bug Fixes), I found a feature related to the fix to allow building schedulers to override block reservations.

With an all day block reservation in place, two events can be scheduled at the same time with the same resources. The happens regardless of how the event was created/moved. i.e. via detail edit, cut/paste, or by dragging and moving.

Essentially, the conflict checking doesn't occur when the all day block is in place. When the block is removed, the events remain scheduled, both using the same resources during the same time period.

Please keep the ability for building schedulers to create events over blocks. Just fix the conflict checking to eliminate possible double booking of resources.
russellhltn
Community Administrator
Posts: 34475
Joined: Sat Jan 20, 2007 2:53 pm
Location: U.S.

#2

Post by russellhltn »

By any chance, were either of these repeating events? I've seen something like that happen in the migration from V1 to V2, a canceled repeating event re-appeared at it's normal time and caused a conflict with another event.
Have you searched the Help Center? Try doing a Google search and adding "site:churchofjesuschrist.org/help" to the search criteria.

So we can better help you, please edit your Profile to include your general location.
dshep2020
Member
Posts: 293
Joined: Mon Jan 22, 2007 11:43 pm

#3

Post by dshep2020 »

No...just single events is I tested.