On the Budget Allowance Detail Report, there is a line called Previous Activity. When and how is this used?

Re: Previous Activity

Posted: Wed Apr 02, 2014 11:19 am
by aebrown
jmlovstedt wrote:On the Budget Allowance Detail Report, there is a line called Previous Activity. When and how is this used?
Budgeting is done on an annual basis. But it is possible to specify a date range for a Budget Report that does not start with January 1. In that case, the Previous Activity row/column (column for a summary report, row for a detail report) will reflect the activity in the subcategory that occurred between January 1 and the beginning date for the report.