Resource assignments not consistently showing up

Posted: Wed Jun 29, 2011 6:29 am
by malewis22062
Hi.

I am the Building Scheduler, so have access to Manage Resource Assignments as well as the normal views of calendars. When I go in via the Calendar view and select the resource I manage in the Subscribed Locations block, I can see calendar events across all three wards where they have reserved the building properly when they created their calendar events. When I go into Manage Resource Assignments for my building, I do NOT see these assignment/reservation, rather just see the "global" resource reservations I created for each Ward's Activity Night (done per instructions in calendar FAQ).

What I really want to be able to do is have a single view I can go to that shows me ALL resource reservations that have been made against the building I manage. I believe this was available in the classic LDS.org calendar. Maybe I'm just not understanding how to do this in the new LDS.org calendar.

Mark

Posted: Wed Jun 29, 2011 6:51 am
by aebrown
malewis22062 wrote:I am the Building Scheduler, so have access to Manage Resource Assignments as well as the normal views of calendars. When I go in via the Calendar view and select the resource I manage in the Subscribed Locations block, I can see calendar events across all three wards where they have reserved the building properly when they created their calendar events. When I go into Manage Resource Assignments for my building, I do NOT see these assignment/reservation, rather just see the "global" resource reservations I created for each Ward's Activity Night (done per instructions in calendar FAQ).

What I really want to be able to do is have a single view I can go to that shows me ALL resource reservations that have been made against the building I manage. I believe this was available in the classic LDS.org calendar. Maybe I'm just not understanding how to do this in the new LDS.org calendar.

There is no single view, although I suppose there could be a use for that. This was not available in the classic calendar, since the whole concept of Resource Assignments didn't even exist. All you could do with the classic calendar was see actual reservations. You can do that in the new Calendar by selecting the building on the main calendar view using "Subscribed Locations."

But an "Assignment" is definitely not a reservation, and you need to make sure you keep those concepts distinct in your mind. You might find some helpful explanations in the thread Double-booking Hazard if "Blocked" was used on "Resource Assignment", where someone was confusing the two issues and some of us tried to help explain the difference.

Posted: Wed Jun 29, 2011 11:38 am
by jdlessley
malewis22062 wrote:What I really want to be able to do is have a single view I can go to that shows me ALL resource reservations that have been made against the building I manage.
This may be available in the 2.0 calendar release. For further information see View Resource Calendar.